Does German buildings insurance pay the extra cost of rebuilding to current regulations?

In short

In current policies usually yes. Under the model terms, version June 2026, these costs are part of the sliding replacement value with no separate limit. Only upgrades to the parts hit by the loss are paid, and rebuilding must be secured within 3 years. Older policies have gaps.

Buildings insurance in Germany (Wohngebäudeversicherung)

What it costs

Premiums from the Stiftung Warentest comparison of November 2026 for a detached house of 150 square metres built in 2005, with natural hazards cover. Limits from published terms.

ExampleTypical range
Model house in Regensburg, very good policiesfrom EUR 635 a year
Model house in Bremen, higher exposurefrom EUR 695, another very good policy EUR 2,822 a year
Extra costs from regulations, model terms June 2026included in replacement value, EUR 0 separate cap
Extra costs for listed buildings, benefits overview 2024EUR 20,000 in the better tier, optional in the basic tier
Remains that may not be reused, 2005 policyEUR 0 without add-on clause

As of November 2026.

Premiums apply to the Stiftung Warentest model case; yours depends on location,

the 1914 value and scope of cover.

The amounts in the worked example are assumed values.

Worked example

Roof fire in a house built in 1968

The roof structure is destroyed. The authority requires today's insulation standard for the new roof. The chimney is still standing but may not be used as it is. The owners would also like to replace the undamaged ground-floor windows.

Rebuilding the roof as it wasEUR 140,000
Extra cost for the required roof insulationEUR 18,000
Replacing the chimney that may not be reusedEUR 6,000
New windows on the undamaged ground floorEUR 15,000, not insured

A policy on current model terms pays EUR 164,000. The 2005 policy without the remains clause pays EUR 158,000. The owners pay the EUR 15,000 for windows themselves in both cases.

What this is about

If the roof burns down or a storm takes out a gable wall, you often may not rebuild the way the house was built. Official requirements (behördliche Auflagen) are frequently stricter today than at the time of construction, for example on insulation, fire safety or structural strength. That costs more than simply restoring the old condition.

German buildings insurance (Wohngebäudeversicherung) owes a house of the same kind and quality. Whether it also pays the surcharge for the new rules depends on the contract alone. The consumer organisation Stiftung Warentest counts this cover among the benefits every policy should include and notes that older contracts often lack such cover.

Situation after the lossCurrent model terms2005 policy we read
New roof must be insulated better than the old oneextra cost included in replacement valuecovered if the law was in force before the loss
Walls still standing may not be reusedcompensated if the order was not issued before the lossnot covered without an add-on clause for remains
Authority had already ordered an upgrade with a deadline before the losscompensation for remains can lapseextra cost not covered
Owner also modernises the undamaged side of the housenot covered, those parts were not damagednot covered
Building prices rise before the rebuildincluded if rebuilding starts without delaycovered if rebuilding starts without delay

What the current model terms say

The model terms of the German insurance association (GDV) for buildings insurance based on the 1914 value are called Gleitender Neuwert Plus in the VGB 2022 edition. According to the preamble, the Plus stands for extra costs from public-law requirements and for price increases between loss and rebuilding. Both belong to the insured value and, for a destroyed building, are paid with the local cost of rebuilding. The model terms set no separate maximum.

If an item can no longer be obtained in the same kind because technology has moved on, replacement value includes a substitute that comes as close as possible. Additional loss of rent caused by the requirements is also named, limited to the agreed number of months. One published policy sets 12 months.

The limits that still apply

First: only the extra cost for parts hit by the loss is paid. If the authority demands thicker insulation for the new roof, that is insured. If you use the building site to insulate the undamaged façade as well, you pay for that yourself.

Second: the portion above current value (Neuwertanteil) is only paid if you ensure that the money is used to rebuild on the same site, and within three years. If rebuilding there is legally impossible or economically unreasonable, a new building elsewhere in Germany is sufficient. Section 93 of the German Insurance Contract Act (VVG) backs such clauses.

Third: if the authority had already issued an order or prohibited use before the loss, compensation for remains that can no longer be used can lapse. A claim is not meant to pay for a conversion that was due anyway.

Why old policies are a risk

A policy wording from 2005 that we read shows the typical gaps. Extra costs are only insured on the basis of laws enacted before the loss. Requirements issued with a deadline before the loss are excluded. And extra costs because reusable remains may no longer be used are not insured unless an add-on clause was agreed.

Newer products go further. One insurer's benefits overview from 2024 lists these extra costs without limit, including remains, in both tiers. The same overview lists extra costs due to listed-building protection separately: optional in the basic tier, up to EUR 20,000 in the better one.

When this matters little for you

For a house only a few years old, today's rules hardly differ from how it was built. The extra cost is then small, and switching policies for this reason alone is not worth it.

The older the house, the wider the gap between then and now. If you own an older building with a policy that has run unchanged for decades, check this point before anything happens. For a listed building the general item is often not enough; you need a specific arrangement.

Step by step

  1. Search your policy terms for Mehrkosten, behördliche Auflagen and Wiederherstellungsbeschränkungen.
  2. Check whether a maximum amount or percentage is stated and whether remains (Restwerte) are included.
  3. Note the year of the terms. If they date from before 2010, ask about an update.
  4. After a loss, pass every order from the building authority to the insurer at once.
  5. Agree the scope of rebuilding with the insurer before you place orders.
  6. Ask the insurer what proof it requires that rebuilding is secured within three years.

Checklist

  • Extra costs from official requirements insured without a fixed maximum
  • Remains explicitly included
  • Extra costs from price increases and technological progress named
  • For a listed building: a separate sum for heritage-related extra costs
  • Loss of rent also covered for delays caused by requirements
  • 1914 value up to date so that no underinsurance deduction applies

Common mistakes

  • Never checking a policy from the 1990s or 2000s for this point
  • Claiming voluntary modernisation of undamaged parts
  • Ignoring an old order from the authority and hoping the next loss will pay for it
  • Waiting more than three years to rebuild
  • Treating listed-building requirements as part of the general item

Questions and answers

Frequently asked

What are official requirements when rebuilding?

Demands by the building authority under the law in force today that the old house did not yet have

to meet.

Typical examples are insulation, fire safety and structural requirements.

Is there a percentage cap?

The current model terms state none; the extra costs are part of replacement value.

Individual contracts may set amounts or percentages.

Your policy schedule decides.

Will the insurer pay for a new heating system if the old type is no longer permitted?

Only if the heating system itself was hit by the loss.

Then, under the model terms, the extra cost of a permitted system is part of replacement value.

An undamaged old system is not replaced.

What if I do not rebuild?

Then under the model terms you only receive the current-value loss.

The portion above current value, which contains the extra costs,

requires rebuilding to be secured within three years.

May I rebuild somewhere else?

Under the model terms yes, if rebuilding on the old site is legally impossible or economically

unreasonable.

The new building must then be in Germany.

Are extra costs for a listed building included?

Not automatically.

One benefits overview we read lists heritage-related extra costs as a separate item of EUR 20,000

or as an optional add-on.

A listed building needs a suitable sum.

Do I have to accept the authority's order?

Whether challenging it is worthwhile is a question for a specialist lawyer.

In any case inform the insurer at once and agree the next steps with it.

Sources

NAMMERT insurance broker

Request a quote: Buildings insurance

We compare insurers and come back to you, in English.

Free; the insurer pays our fee.

Related questions